DDSEAR Audit

Observations

322 observations

A — Reduce dangerous substances to a minimum

Whole row

Types and quantities do not exceed activity requirements

High standard of housekeeping

A maximum of 250 litres of flammable liquids only is stored in one workroom, of which 50 litres may be highly flammable

Periodically review necessity of using flammable solvent borne spray paints and thinners to reduce risk ALARP

Confirmation of maximum flammable substances input to be sought from manufacturer’s information

Review inventory of legacy hazardous substances and remove redundant stocks

Not in use containers of flammable liquids to secure, spill containing, fire resistant cabinets / chests

Bins emptied regularly

B — Avoid or minimise release

Whole row

Substances stored appropriately in single layers within storage enclosures

Press equipment placed on critical items register and recorded service contracts arranged with specialist sub-contractor

VOC and over temperature alarms shut-down the heating system but keep the ventilation system operating, and that they are to level PL d

Minimum exhaust flowrate of 469m3 /h for drying tunnel

Spill containing safety containers at usage areas

Ductwork maintained in good condition

Flange guards to pressurised pipework

Overcharging under fault conditions is prevented

Storage cage for aerosols

Filters are fitted within airflow alarms

Gas equipment placed on critical items register and recorded service contracts arranged with specialist sub-contractor

Vehicle impact protection barriers to roadway side of diesel tank

Review maintenance and leak prevention for pumps, rotating, and process equipment

Corrosion to pipework, fittings and tank

Small solid fuel heater placed on critical items register and recorded service contracts arranged with specialist sub-contractor

Oil fired heater placed on critical items register and recorded inspection and service contract arranged with specialist sub-contractor

UV equipment placed on critical items register and recorded service contracts arranged with specialist sub-contractor

Review effectiveness of dust extraction systems

Tank and dispenser placed on critical items register and ensure recorded inspection and service contract arranged with specialist sub-contractor

Pipework correctly coloured and/or identified

Biomass plant placed on critical items register and recorded service contracts arranged with specialist sub-contractor

Satisfactory operation of excess high / low condition switches and alarms

Alarm switches placed on critical items register and recorded service contracts arranged with specialist sub-contractor

Dust collector equipment placed on critical items register and recorded service contracts arranged with specialist sub-contractor

Maximum flammable substances throughput of drying tunnel as less than 4,250g/h

Transport methods for larger containers prevent spillage of flammable liquids

Heating oil tank placed on critical items register and recorded inspection and service contract arranged with specialist sub-contractor

Cell terminals effectively guarded against inadvertent short circuits

Trays / lipped edges to mixing tables and benches

Review maintenance and leak prevention for equipment connections and access hatches

Spray equipment placed on critical items register and recorded service contracts arranged with specialist sub-contractor

Flexible dust and hoses are correctly installed and replaced if damaged

Corrosion to gas pipework

Gas pipework sleeved where it enters buildings or passes between building compartments

Covers are in place and hatches are closed so that loss of containment is minimised for process equipment

Pipework sleeved where it passes through walls

Woodworking machinery placed on critical items register and recorded service contracts arranged with specialist sub-contractor

C — Control release at source

Whole row

AIVs to gas incoming supplies to buildings

Use of top mounted dispensing pumps for medium and large containers

Receiver tanks and distribution system placed on critical items register and recorded service contracts arranged with specialist sub-contractor

Drying tunnel placed on critical items register and recorded service contracts arranged with specialist sub-contractor

Remote indication for dust collection plant status and alarms

Decanting: Flammable solvent inventory within the area should be minimised / controlled at all times

Only required materials are moved from storage locations

Battery using equipment on critical items register and ensure recorded service contracts arranged with specialist sub-contractor

Heating system shut-down in event of control system failure

Decanting: Limit the flow rate

Decanting: Avoid splashing where possible

Dust extraction and collection systems are interlocked to functioning of required machinery

Use metallic funnels and static dissipative hoses as required

Decanting: Avoid open containers / faulty containers and subsequent vapour potential at all times

Decanting: Ensure adequate earthing for dispensing / decanting of flammable solvents.

Temperature and air flowrate achieved prior to charging operations

Confirmation of drying ranges to be sought from manufacturer’s information

Isolation valves are identified and operable

Mechanical extract ventilation system interlocked with the drying tunnel controls

Shut-down sequence function implemented to drying tunnel operations

Extract duct valves that are capable of controlling airflows satisfactorily

Satisfactory operation of control system inputs and outputs and associated control equipment

Equipment functions as designed, so as to minimise loss of containment at cutting / trimming / MEV / extraction equipment

Decanting: Utilise secondary containment / bunded trays or similar for holding flammable containers

Purging sequence function implemented to drying tunnel operations

Mechanical extract ventilation system interlocked with the spray equipment controls

Hazardous liquids stood on secondary spill containing pallets / trays

Battery charging equipment on critical items register and ensure recorded service contracts arranged with specialist sub-contractor

All storage enclosures are locked when not in use

Decanting: Use only metallic containers

Decanting: Ensure adequate ventilation for dispensing / decanting of flammable solvents.

D — Prevent formation of an explosive atmosphere, including ventilation

Whole row

VOC and over temperature alarms shut-down the heating system but keep the ventilation system operating, and that they are to level PL d

8 – Strengthening of critical ductwork to resist over-pressure and contain it so that the relief vents operate as designed

The exhaust air ducts feature adequate access for inspection and maintenance

Rapid cycling ignition scenarios are added to operating manual and training material

Differential air-flow detection and alarm across filter unit

Adequate fresh air inlets from exterior provided

Extraction from low level available to collect heavier than air vapours

Spray booth ventilation systems are placed on critical items register and service contracts arranged with competent specialist sub-contractor

Ventilation louvres kept clear

Ventilation to enclosed store rooms and open stores is adequate and achieves 0.1m/s and 5ACH

10 – Exhaust heights to meet local authority guidelines

2 – Anti-static filters to replace standard units

4 – Differential pressure monitoring, alarm, and shutdown on filter controllers

Ventilation rates around forklift batteries under charge are adequate

Suitably EX rated mechanical extract ventilation systems (MEV) implemented to extract the dust and collect it in external units, or the features below to be verified or installed to existing systems. The MEV to feature:

Dust MEV systems are placed on critical items register and service contracts arranged with competent specialist sub-contractor

6 – Overpressure relief vents relieving to a place of safety away from personnel routes or critical equipment

Ventilation measures periodically reviewed for adequacy as regards process and production activities

7 – Shut-off damper on ductwork to prevent dust explosion passing back into building

Failed ignition scenarios are added to operating manual and training material

Implementation of VOC monitoring system to internal mixing and use areas

Smoke clearance test required to be carried out as part of thorough written scheme of examination

The ventilation system recirculates warm air throughout the total volume of the drying tunnel

Dust extraction to woodworking activities is adequate and achieves required rate

MEV systems do not automatically re-start after a power failure

1 – All metallic parts earthed in such a manner that the earth path back to reference point can be measured. Usually by use of earth bonds across joints, with two paths being specified, so that when one is disconnected for testing the other still functions

Sufficient inspection frequency

Visual and audible airflow alarm indication is present and adequate for the extent of the booth

Ventilation to open spray booth is adequate, and that the average of measured air velocities is at

Ventilation to workshop activities is adequate and achieves 0.5m/s and 12ACH

Induced draft fan interlocked to operation of biomass unit

Manual intervention scenarios included in existing operating manual and training material

EX rated MEV systems to flammable substances storage and use areas

Drying tunnel ventilation system is placed on critical items register and service contracts arranged with competent specialist sub-contractor

Adequate ventilation in place in at bottom shed press heater

Hazardous waste stored in external well-ventilated location

MEV systems interlocked to functioning of required process equipment

Input of flammable substances is monitored

Vapour MEV systems are placed on critical items register and service contracts arranged with competent specialist sub-contractor

3 – Temperature detection, alarm, and shutdown on critical rotating parts

Extraction points to process equipment connected to vapour extract systems using fixed ductwork

5 – Use of materials and methods to offer inherent mitigation of likelihood of production of sparks, such as greater clearances, brass rubbing strips on shafts

9 – Provision of explosion isolation device at outlet (rotary valve) if required

E — Collect, contain or remove any release

Whole row

Minimum exhaust flowrate monitoring devices installed to drying tunnel

Fans and ducts thoroughly cleaned of paint residues

Forced ventilation system run-on in event of safety system failure

Ventilation louvres are kept clear

For releases of a dangerous substance, ensure measures to contain or collect or remove to a safe place are documented, and reviewed periodically

All biomass boiler incidents are reported

Investigate whether interceptor installed to collect fuel spillages

Use vacuum cleaner as required to ensure surfaces and ledges are regularly cleaned to remove dust accumulations

Areas are kept free of obstructions

Filters are changed when differential pressure readings cross thresholds

Periodically review and ensure satisfactory performance of dust extraction and collection systems

Vapour extract vents are at least 3 metres above ground level, and 3 metres from sources of ignition and building openings

Heating system shut-down in event of forced ventilation failure

Spill kit available in area

Heating system interlocked to monitoring device

Forced ventilation system run-on in event of heating failure

F — Avoid ignition sources

Whole row

All lighting is of sealed type

Alternatively, implement ventilation failure alarms and gas detection alarms, and install a safety isolating contactor to remove power to the UV equipment in event of alarm

Dust extraction flexible ducts feature metal filaments, and that these are earth bonded at both ends

Earth resistance of circuit protective conductors for any electrical equipment

Spray booth floor resistance does not exceed 1006 Ohm

EX equipment on critical items register and ensure recorded service contracts arranged with specialist sub-contractor

If dryer operates in Range 3, ensure equipment and installations meet ATEX category 2G

Electrical switches, contactors and relays remove power from both phase and neutral conductors

Adequate identification of main isolation points

Where vacuum cleaners are used in dusty environments, ensure these are suitably EX rated

Electrical and mechanical equipment within Hazardous Areas is suitably EX rated

Vapour extract LEV/MEV system will require suitably EX rated fan assemblies

Robust barriers installed to cable and pipework routes between Hazardous Areas and non-Hazardous Areas

Electrical circuits adequately identified

Delivery tanker earthing point

Earthing system for EX electrical installation is TN-S, IT or TT, not TN-C, TN-C-S

Battery powered equipment is isolated prior to charging

Potential hot surfaces of the tunnel are prevented from contacting the drying items

Where earth connections exist, these should be on a recorded schedule of earth resistance measurement

EX equipment is installed as per the X conditions on accompanying ATEX certificates

If dryer operates in Range 2, ensure equipment and installations meet ATEX category 3G

Biomass feed system to be suitably EX rated

Static dissipative footwear and clothing, mats, and floor coatings

Large lead-acid batteries are separated from sources of ignition by at least 1 metre

Vehicle ignition systems switched off during refuelling

Install suitably EX rated lighting, fans and power and alarm circuits to flammables storage and mixing areas

Electrical and mechanical equipment properly maintained so as to prevent being a source of ignition

Implementing lightning protection system to tall external structures (exhaust vents)

No sources of ignition within separation distances of flammable substances storage and use locations

The MEV fan features spark minimizing bearings and anti-static blades

All plant, equipment and structures adequately earthed

Rigorously control / separate flammables from personal sources of ignition

Auto-ignition cannot occur by provision of temperature monitoring and shutdown controls

Electrical installation within area is approved by EX certified electrical supervisor

Overheating cannot occur by provision of temperature monitoring and shutdown controls

G — Avoid adverse conditions causing harmful physical effects

Whole row

Robust metal baffle plates around internal bag dust collectors to deflect flame away from occupied areas

VOC/gas monitoring to drying tunnel

Electrical and electronic equipment competently installed so as to prevent external influences adversely affecting safety performance of equipment

VOC/gas monitoring system equipment on critical items register and ensure recorded service contracts arranged with specialist sub-contractor

Eye wash stations present at battery charging areas

The equipment within the spray booth or drying tunnel that is reachable by operatives is correctly installed and maintained in good working order, and there is no possibility of contact with hot parts

Employee exposure limits are not exceeded by use of appropriate barriers, ventilation and if necessary, PPE

Flammable liquids containers shielded from sunlight if stored externally

Adverse conditions are avoided by use of appropriate detection, isolation, ventilation and if necessary, PPE

Electrical equipment competently installed so as to prevent being a source of ignition or electric shock

RPE fits correctly and is periodically checked for satisfactory functioning

The lighting level meets 750 lux

Implementing portable gas monitoring equipment

Implementing carbon monoxide (CO) gas detection and alarms at fired appliance areas

H — Segregate incompatible substances

Whole row

Different waste types are effectively managed to separate waste streams

Hazardous waste disposed using licenced waste carrier with consignment note received

Safe working instructions for mixing and use of different classes of hazardous substances are followed

Structural steelwork protected from spill of corrosive fluids

Minimum separation distances between different classes of hazardous substances are observed

I — Reduce number of employees exposed

Whole row

Review and minimise personnel attendance at hazardous substances locations

J — Avoid propagation of fires or explosions

Whole row

Excess combustible material removed from storage and production areas

Excess combustible material removed from gas incomer and metering and appliance areas

Combustible material not stored in compressor areas

Combustible material and vegetation removed from around heating oil tank area

Bins are suitably fire resistant

Partitions are suitably fire rated such that propagation of fires or explosion is contained as required for the facility

Combustible material removed from spray areas

The spray booths meet the criteria for fire safe construction, including materials of construction of the filter cartridges

Excess combustible material removed from drying tunnel area

Excess combustible material removed from biomass plant area

Annual review of Fire Risk Assessment

The drying tunnel meets the criteria for fire safe construction, including materials of construction of the filter cartridges

Where not fitted, seriously consider implementing rotary valves to assist with explosion isolation

Combustible material removed from around diesel fuel tank area

Replacing spiral wound ductwork with smooth walled type

Stores are located such that propagation of fires or explosion is contained as required for the facility

Minimum separation distances for external storage locations are implemented

BS EN 14470 flammables cabinets as required

Excess combustible material removed from dust collector areas

Excess combustible material removed from woodwork machining areas

2 hour fire barrier along boundary fence

Combustible material removed from battery charging areas

Seriously consider relocating internal dust collectors to external locations, away from occupied work areas

K — Explosion relief

Whole row

Review explosion relief arrangements for the dust extraction equipment

Explosion relief vents are placed on critical items register and service contracts arranged with competent specialist sub-contractor

Explosion relief vents to dust extraction equipment

Explosion relief vents relieve to a place of safety away from personnel routes or critical equipment

Pressure relief valves on critical items register and checked by specialist sub-contractor at appropriate interval

Non-EX rated safety devices with suitably EX rated items

L — Explosion suppression

Whole row

Water quench system placed on critical items register and recorded service contracts arranged with specialist sub-contractor

M — Plant built to withstand explosion pressure

Whole row

N — Personal protective equipment

Whole row

Correct PPE provided and worn by personnel

O — Raise alarm and shut down from a safe place

Whole row

Remote emergency shutdown controls at least 3 metres from dust collector

Emergency shutdown and alarm systems are placed on critical items register and service contracts arranged with competent specialist sub-contractor

Means of shutting down systems from a safe place provided and readily identified

Means of raising alarm from a safe place provided and readily identified

P — Means of escape

Whole row

Fire-fighting equipment placed on critical items register and service contracts arranged with competent specialist sub-contractor

Emergency lighting placed on critical items register and service contracts arranged with competent specialist sub-contractor

Adequate fire-fighting equipment provided in area

Adequate illumination provided for non-daylight hours or emergency evacuation

Sufficient fire water capacity available

Q — Signage

Appropriate warning signage at hazardous locations

Specific EX signage present at entrances to or around Hazardous Areas

R — Information, instruction and training

Whole row

Procedures for safe operation and maintenance

Staff in COSHH & DSEAR risks

S — Information for emergency services

Whole row

Inventories of dangerous substances

Hazardous locations on site emergency response plan

Gas distribution schematic

T — Organisational measures

Review flammable gases, liquids and dusts delivery offloading and handling procedures

Review site materials SDS, and minimise inventories

Review site emergency response plan and include DSEAR risks

Review DSEAR arrangements & controls after a significant plant change and/or a period of THREE years has elapsed

Review Management of Change procedures

DSEAR training at appropriate levels

Review work instructions for DSEAR activities

Review work instructions (PTW) and hot work permit arrangements